Servicing the entire Sunshine Coast from Caboolture to Gympie

Fruit Shop – Maroochydore

Case Study

Brief

Engaged by the landlord to provide up to date assessment and report on current condition of equipment and systems within tenancy after 2-3 years out of operation.

In-tern, engaged to replace several complete systems and return the site to full operation

Details

Supplied and installed a new 28kw Coldroom system including 50m of new pipework and insulation

Decommissioned and disposed of all unrequired refrigeration, mechanical and electrical equipment

Supply and installation of multiple split system air conditioning units

Replacement of 25kw compressor in the existing packaged air conditioning unit

Retro fit of existing air conditioning ductwork to suit new tenancy layouts

Outcome

Customer was able to move in and initiate fit out before schedule with all systems operational as required